• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Columbine Valley Town logo

Columbine Valley Colorado

  • Community
    • Calendar
    • Events & Services
      • 4th of July Parade & Festival
      • Summer Concerts in the Park
      • Scooter & Bike Safety Training
      • Fall Leaf Dropoff
      • Flu Shot Clinic
      • Prescription Drug Take-Back Events
      • Shred Events
    • History
    • Maps
    • Newsletters
    • Parking & Overnight Permits
    • Camper/RV Parking
    • Dogs: Leash Law, Licensing & Limit
    • Dumpsters, Etc.
    • Garage, Yard & Estate Sales
    • HOAs
    • New Residents
    • Report a Concern
    • No Solicitation / No Visit List
      • Solicitation FAQs
  • Government
    • Government Overview
    • What We Don’t Do
    • Mayor & Board of Trustees
      • Board of Trustees Agendas & Minutes
    • Commissions
      • Planning & Zoning Minutes & Agendas
    • Public Meetings
    • Town Staff
    • Employment
    • Get Involved
    • Town Documents
    • Tax Rate
    • Budgets & Finances
  • Police
    • Police FAQs
    • House Watch
    • Parking & Overnight Permits
    • Records & Reports Request
    • Mail Theft & Identity Theft
    • Golf Carts
    • Witness Statement
    • Employment
  • Court
    • Municipal Court
    • Pay Ticket
    • Request a Continuance
    • Court FAQs
  • Public Works
    • Intrepid Fiber Installation
    • Trash & Recycling
    • Snow Removal
    • Stormwater & Floodwater
    • Street Maintenance
    • Parks & Open Space
    • Right of Way
    • Mosquito Management
    • Wildlife & Animal Control
    • Capital Improvement Program
    • Public Works FAQs
  • Building
    • Building Permits
    • Other Permits
    • Inspections
    • Sales Tax & Use Tax
    • Contractor Licenses
    • Building Codes
    • Fee Schedule
    • Stormwater Runoff
    • Building Department FAQs
  • Happening Now

Street Maintenance

Wild Plum Asphalt Mill & Overlay: 

Weather Update

Due to wet weather this week, milling is taking longer than originally scheduled. Milling on Wild Plum Lane and Wild Plum Court will continue on Saturday, May 9.  Paving on Latigo is expected to begin around May 12 and continue as planned.

Work Scheduled for May 4–19

As part of the probationary acceptance process, the Wild Plum developer, Lennar Homes, will complete a mill and overlay on all internal Wild Plum streets. Lennar Homes is responsible for managing this project and has provided the following information.

Please Remember: All road work is dependent on weather, equipment, crew availability, and other factors. Dates and schedules are subject to change.

Parking and Vehicle Access: Residents may experience periods of limited parking and vehicle access while work is being completed on their street.

  • Please notify any contractors, such as cleaning services, painters, landscapers, or other service providers, about possible parking changes.
  • No Parking signs will be placed on streets before work begins to let residents know when their street is scheduled for repair.
  • Because vehicle access may be limited at times, overnight parking will be allowed on Fairway Lane near the Damsire Drive intersection during the project. The police will not ticket vehicles parked in this area for the duration of the project.

No Street Closures: No street closures are currently planned.

  • Residents should allow extra time when traveling through the construction area.
  • Flaggers will be on site to help direct traffic.
  • For the safety of the crew and to help ensure quality work, please be patient and follow all traffic control instructions.

Driving After Milling: After the streets are milled, please use extreme caution while driving.

  • There will be an approximately 2-inch drop from concrete gutter pans and driveways to the milled asphalt surface.
  • Manholes and water valves will also be approximately 2 inches higher than the milled surface.
  • Loose debris may also be present on the roadway.

Damsire Drive and Fairway Lane Intersection: Although all work is occurring on internal Wild Plum streets, this intersection will be impacted.

  • During the project, the intersection of Damsire Drive and Fairway Lane may have temporary dips or bumps.
  • Please use caution when driving through this intersection.

Week 1, May 4–8: Milling & Patching

The top 2 inches of asphalt will be milled and removed from all Wild Plum streets. The planned milling order is:

  1. Latigo Place
  2. Wild Plum Lane and Wild Plum Court
  3. Wild Plum Lane and Hunter Run Lane
  4. Damsire Drive

Additional asphalt patching is scheduled at multiple locations.

Paving of Latigo Place may take place on Friday, May 8.

Week 2, May 11–15: Paving

Paving is scheduled for all remaining streets. The planned paving order is:

  1. Latigo Place
  2. Wild Plum Lane and Wild Plum Court
  3. Wild Plum Lane and Hunter Run Lane
  4. Damsire Drive

Week 3, May 18–22: Stop Bar Painting

Stop bars will be painted at all stop signs with work expected to finish by May 19.

For questions during normal business hours, please contact Town Hall at 303-795-1434.

5 Tools for Street Maintenance Updates

Please know that Public Works is committed to providing timely information about maintenance that impacts resident parking and driving within the Town. Keep in mind that schedules do change rapidly due to issues such as weather and crew availability. The Town communicates about street maintenance in the following ways:

  1. Website: This page is updated first and serves as the one source of truth of street maintenance.
  2. Email: The aim is to send a targeted email to affected residents when work begins in an area. All residents for whom we have an email address receive a message. If you’re not on the Town email list, send a note to KAnton@ColumbineValley.org.
  3. Door Tags: When significant work is planned, Public Works places a note on the front door of each impacted house. If you’re in the habit of entering through the garage, you might check the front door occasionally.
  4. Nextdoor: Find general updates on street maintenance at nextdoor.com/pages/town-of-columbine-valley.
  5. HOA Presidents: If a major and/or time-consuming project will occur in a neighborhood, Staff will communicate with the HOA President so he or she can cascade the information to their residents.

For questions, please call Town Hall at 303-795-1434 during regular business hours, Monday–Friday, 8 a.m.–1 p.m.

Primary Sidebar

Contact Us!

Town Hall:
2 Middlefield Road
Columbine Valley, CO 80123

Phone: 303-795-1434
Dispatch: 303-795-4711

Business Hours:
Monday through Friday
8 a.m. – 1 p.m. or by appointment

Footer

Connect with Us

Address: 2 Middlefield, Columbine Valley, CO 80123
Phone: 303-795-1434 | Dispatch: 303-795-4711

Our Newsletters

Take a look at our past newsletters to learn more about our community, our events and more.

Read the news

Website Disclaimer

The Town of Columbine Valley operates and maintains this official website to provide citizens and visitors with information about Town programs, services, projects, issues, events and activities. This information is intended to offer quick, convenient and easy access for those wishing to learn about the Town of Columbine Valley. The Town website is administered and maintained through the Town Administrator’s Office. The Town’s staff updates the website regularly and every effort has been made to ensure the accuracy of the information provided on the site. The information is provided as a public service, and the Town of Columbine Valley assumes no liability for any inaccuracies the website may contain. Please feel free to notify the Town of Columbine Valley of any errors you discover on the website.